2021 Authorizations

Date of Event Applicant Purpose Community Benefit
Oct 1 2019 to Mar 1 2021 Soletanche Bachy Canada - Dockwall Repairs Times: Daylight Hours
Location: Dockwall Repair to the north side (eastern end) of the Western Channel
Dockwall Replacement
Jan 6 2020 to Aug 30 2024 Toronto and Region Conservation Authority Landform Construction Projects, includes infill, berm and breakwater construction
Location: Ashbridge's Bay
Protection of shoreline erosion and reduce dredging requirement at Ashbridge's Bay
Jan 2020 to Dec 2023 Ellis Don Operation of water discharge structure
Location: Ship Channel
Waterfront Toronto's Portlands Flood Protection Project
Mar 4 2020 to Dec 31 2023 Toronto and Region Conservation Authority Breakwater Construction Project
Location: Ashbridge's Bay
Protection of shoreline erosion and reduce dredging requirement at Ashbridge's Bay
Nov 20 2020 to May 31 2021 Toronto and Region Conservation Authority Construction of reef and placement of rip rap materials
Location: Ashbridge's Bay
Protection of shoreline erosion at southeast side of Ashbridge's Bay
Nov 27 2020 to Nov 16 2021 Ellis Don Operation of water intake
Location: various Portland locations
Waterfront Toronto's Portlands Flood Protection Project
Dec 7 2020 to Apr 12 2021 Island Yacht Club Annual request to Install and remove a boardwalk during the winter months
Location: Between Muggs Island and Centre Island
Providing ability for Island Yacht Club employees to access required facilities
Jan 12 to Feb 26 2021 McNally Construction Removal of 92m water pipe
Location: Long Pond
Providing safe and navigable waters to boaters
Feb 22 to May 31 2021 Toronto and Region Conservation Authority Construction of aquatic habitat
Location: northside of Tommy Thompson Park
Providing and sustaining a natural environment for the enjoyment of the community
Mar 5 to Dec 31 2021 Toronto and Region Conservation Authority Environmental monitoring activities including water / sediment sampling
Location: the jurisdiction of the Toronto Port Authority
Environmental Studies benefiting the Toronto Harbour
Mar 19 to Dec 31 2021 Riggs Engineering Ltd. Collection of sediment samples and bathymetric survey data
Location: Various locations in the harbour, including Coronation Park, Keating Channel, Polson Slip and Outer Harbour
Environmental Studies benefiting the Toronto Harbour
Apr 1 to Oct 1 2021 University of Toronto Environmental monitoring of floating litter and plastics from various pathways into the Toronto harbour Environmental Studies benefiting the Toronto Harbour
Apr 6 to May 10 2021 Geophysics GPR International Inc. Collection of bathymetric and seismic survey data
Location: Yonge St Slip, Parlaiment St Slip and Jack Layton Ferry Slips
Waterfront Toronto's Queens Quay East Extension and Jack Layton Ferry Terminal Project
Apr 21 to May 21 2021 Terrapex Environmental Ltd. Borehole drilling
Location: Yonge and Parlaiment Street and Jarvis and Parlaiment Street Slips
Waterfront Toronto's Portlands Flood Protection Project
Apr 28 to Jun 30 2021 QM Environmental Polson Slip Dockwall Demolition Demolition and construction done in conjunction with the Portland Flood Protection Project

 

Boaters Notice

PortsToronto is responsible for keeping the Toronto Harbour safe and navigable. See Boater’s Notices about everything from swimming in the harbour to obtaining permission for a marine event.